PERMIT #7105090-CN
10013 RICHWOOD AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 30, 2025
In Review
3 cycles
Reviews Done
February 10, 2026
Ready to Issue
February 10, 2026
Issued
February 11, 2026
Completed
—
Expires
August 11, 2027
103
Plan Review Days — Total
74
Plan Review Days — City Control
29
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$19,500
Type
Residential Construction
Issued
February 11, 2026
Location
Crown Hill
Contractor Information
Location & Map
Project Description
Scrivanich Deck Repair Construct alterations to west side and deck of existing single-family residence, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
KARLSA*791D5
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1140664
Review cycles
3
Plan review days
103
Days in corrections
29
Expires
August 11, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0