PERMIT #7105228-CN

215 N 125TH ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 28, 2025
In Review
2 cycles
Reviews Done
February 17, 2026
Ready to Issue
February 17, 2026
Issued
February 20, 2026
Completed
July 16, 2026
Expires
August 20, 2027
112
Plan Review Days — Total
21
Plan Review Days — City Control
91
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Broadview Neighborhood

Project Overview

Project Details
Value
$25,000
Type
Commercial Construction
Issued
February 20, 2026
Location
Broadview

Contractor Information

Contractor
MASTEC NETWORK SOLUTIONS INC
General Contractor
License MASTENS876KN

Location & Map

Project Description
BITTER LAKE 2 - WSWOR0049271 Alterations to existing minor telecommunications facilities (AT&T) at ground level and monopole, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MASTENS876KN
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0016125
Review cycles
2
Plan review days
112
Days in corrections
91
Expires
August 20, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →