PERMIT #7105367-CN
2733 4TH AVE S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
November 17, 2025
In Review
2 cycles
Reviews Done
December 22, 2025
Ready to Issue
December 22, 2025
Issued
December 26, 2025
Completed
January 27, 2026
Expires
June 26, 2027
35
Plan Review Days — Total
22
Plan Review Days — City Control
13
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2733 4TH AVE S, SEATTLE, WA Property
Renovation at 2733 4TH AVE S Project
HYBRID ASSEMBLY LLC Contractor
SoDo Neighborhood
Project Overview
Project Details
Value
$500
Type
Commercial Construction
Issued
December 26, 2025
Location
SoDo
Contractor Information
Location & Map
Project Description
2733 4th ave S. Change of use from retail sales to marijuana processing per the land use code, Construct alterations in a mixed-use building for same in SE ground level tenant space, occupy per plans.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HYBRIAL902KR
Review level
Full +
Primary use
Commercial
Parcel
DV0034759
Review cycles
2
Plan review days
35
Days in corrections
13
Expires
June 26, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0