PERMIT #7105883-CN

521 STADIUM PL S, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
November 7, 2025
In Review
2 cycles
Reviews Done
January 6, 2026
Ready to Issue
January 12, 2026
Issued
January 13, 2026
Completed
May 20, 2026
Expires
July 13, 2027
60
Plan Review Days — Total
20
Plan Review Days — City Control
40
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$95,000
Type
Residential Construction
Issued
January 13, 2026
Location
Other Seattle

Contractor Information

Contractor
VENTURE GENERAL CONTRCTNG LLC
General Contractor
License VENTUGC899LZ

Location & Map

Project Description
MultiFamily Renovation Construct alterations to lobby and leasing offices at levels 1 and 2, South Tower (WAVE tower), of existing mixed-use building, per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VENTUGC899LZ
Review level
Full +
Primary use
Multifamily
Parcel
DV0078423
Review cycles
2
Plan review days
60
Days in corrections
40
Expires
July 13, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor