PERMIT #7105948-CN

2119 E PINE ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
September 18, 2025
In Review
3 cycles
Reviews Done
January 2, 2026
Ready to Issue
January 5, 2026
Issued
January 5, 2026
Completed
Expires
July 5, 2027
106
Plan Review Days — Total
34
Plan Review Days — City Control
72
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Capitol Hill Neighborhood

Project Overview

Project Details
Value
$22,355
Type
Residential Construction
Issued
January 5, 2026
Location
Capitol Hill

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
1475 22nd Ave DADU (Establish use as a detached accessory dwelling unit, per land use code.) Construct substantial alterations to existing detached accessory building to create a new one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1212292
Review cycles
3
Plan review days
106
Days in corrections
72
Expires
July 5, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
1
Open official SDCI detail →
Open Map