PERMIT #7105987-BK

900 4th Ave, Seattle, WA

Completed

StateFarm Construct blanket permit tenant improvements to State Farm on the eighth floor of existing commercial building at 900 4th Ave, Seattle, WA in Downtown, Seattle. Permit 7105987-BK is completed, valued at $359,900. Work is being performed by GATEWAY CONSTRUCTION SRVCS INC.

Permit Timeline & Status

Construction Permit Timeline
AppliedSeptember 10, 2025
In Review2 cycles
Reviews DoneSeptember 30, 2025
Ready to IssueOctober 1, 2025
IssuedOctober 7, 2025
CompletedFebruary 13, 2026
ExpiresApril 7, 2027
20
Plan Review Days — Total
20
Plan Review Days — City Control
0
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$359,900
Type
Commercial Construction
Issued
October 7, 2025
Location
Downtown

Contractor Information

Contractor
GATEWAY CONSTRUCTION SRVCS INC
General Contractor
License GATEWCS992C3

Location & Map

Development site
DV0027816
Site area
59,345 sq ft
Site status
ACTIVE
Source updated
Dec 22, 2016
Last checked
Nov 28, 2026

Current SDCI site context. The outline shows the development-site boundary used for code standards.

Official Seattle development-site data →
Project Description
StateFarm Construct blanket permit tenant improvements to State Farm on the eighth floor of existing commercial building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GATEWCS992C3
Review level
Full C
Primary use
Commercial
Property reference
DV0027816
Review cycles
2
Plan review days
20
Days in corrections
0
Expires
April 7, 2027
Open official SDCI detail →
View Contractor