PERMIT #7106106-CN
3603 34TH AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 11, 2025
In Review
0 cycles
Reviews Done
November 10, 2025
Ready to Issue
November 12, 2025
Issued
November 12, 2025
Completed
—
Expires
May 12, 2027
60
Plan Review Days — Total
60
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$1
Type
Residential Construction
Issued
November 12, 2025
Location
Magnolia
Contractor Information
Location & Map
Project Description
Construction Permit EAST single-family dwelling unit will remain per land use code. (Single family dwelling unit will remain per land use code. Construct one family dwelling, per plan. Review and processing for (2) records under 7070519-CN.)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
EXSTAL*775LT
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV1202281
Review cycles
0
Plan review days
60
Days in corrections
0
Expires
May 12, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0