PERMIT #7106125-CN

118 BROADWAY E, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 10, 2025
In Review
0 cycles
Ready to Issue
September 15, 2025
Issued
September 15, 2025
Completed
April 2, 2026
Expires
March 15, 2027
0
Days in Applicant Control
0
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$45,000
Type
Commercial Construction
Issued
September 15, 2025
Location
Capitol Hill

Contractor Information

Contractor
WEST SUMMIT GNRL CONTRNG LLC
General Contractor
License WESTSSG780JL

Location & Map

Project Description
Construct Interior non-structural alterations to existing B occupancy restaurant per STFI

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
WESTSSG780JL
Housing category
Commercial Add/Alt
Review level
Field
Primary use
Commercial
Parcel
DV0082051
Review cycles
0
Days in corrections
0
Expires
March 15, 2027
Open official SDCI detail →
View Contractor