PERMIT #7106135-CN
1615 42ND AVE E, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 10, 2025
In Review
0 cycles
Reviews Done
March 11, 2026
Ready to Issue
March 11, 2026
Issued
March 11, 2026
Completed
—
Expires
September 11, 2027
182
Plan Review Days — Total
182
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$412,146
Type
Residential Construction
Issued
March 11, 2026
Location
Madison Park
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit New project description (MIDDLE UNIT RECORD): Construct MIDDLE new one family dwelling (SFR2), per plan. (Establish use as (3) single family residences per land use code. Construct (3) new one family dwellings, per plan. Review and processing for three records under 7090525-CN.)
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV0042054
Review cycles
0
Plan review days
182
Days in corrections
0
Expires
September 11, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0