PERMIT #7106185-CN

3520 ASHWORTH AVE N, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 16, 2026
In Review
2 cycles
Reviews Done
May 29, 2026
Ready to Issue
May 29, 2026
Issued
June 9, 2026
Completed
Expires
133
Plan Review Days — Total
65
Plan Review Days — City Control
68
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$471,311
Type
Residential Construction
Issued
June 9, 2026
Location
Other Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct WEST one-family dwelling (SFR 1) per plan. ([LAND USE TO CONFIRM DESCRIPTION: Establish use as (2) single-family residences per land use code.] Construct (2) one-family dwellings per plan. Review and processing for (2) records under 7106185-CN.)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1100313
Review cycles
2
Plan review days
133
Days in corrections
68
Units added
2
Units removed
0
Open Map