PERMIT #7106225-CN
1912 29TH AVE S, Seattle, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 25, 2025
In Review
2 cycles
Reviews Done
October 16, 2025
Ready to Issue
October 16, 2025
Issued
October 21, 2025
Completed
—
Expires
April 21, 2027
21
Plan Review Days — Total
16
Plan Review Days — City Control
5
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$20,000
Type
Residential Construction
Issued
October 21, 2025
Location
Mt Baker
Contractor Information
Location & Map
Project Description
Wilcox Robbins Drive & Entry Walk Construct retaining walls, widen driveway, and perform associated site improvements, accessory to existing single family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HOUSECC093L6
Housing category
Single-Family Add/Alt
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV1095018
Review cycles
2
Plan review days
21
Days in corrections
5
Expires
April 21, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0