PERMIT #7106473-CN
1505 6TH AVE S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
October 16, 2025
In Review
0 cycles
Reviews Done
October 28, 2025
Ready to Issue
October 28, 2025
Issued
October 28, 2025
Completed
November 3, 2025
Expires
November 28, 2025
12
Plan Review Days — Total
12
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1505 6TH AVE S, SEATTLE, WA Property
Renovation at 1505 6TH AVE S Project
GRANITE CONSTRUCTION COMPANY Contractor
SoDo Neighborhood
Project Overview
Project Details
Value
$45,000
Type
Commercial Construction
Issued
October 28, 2025
Location
SoDo
Contractor Information
Location & Map
Project Description
KC000225-EAGLE VILLAGE TEMP OFFICE TRAILER (2 of 6 max at this location for use through 11/28/2025 this record) to: Install 5 (five) factory built/office trailers and 1(one) bathroom trailer as temporary structures for use as construction offices/support for nearby King County project (6th Ave. South Yard Renovation) for 4 weeks, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GRANICC916DL
Review level
Dependent Building
Primary use
Commercial
Parcel
DV0068411
Review cycles
0
Plan review days
12
Days in corrections
0
Expires
November 28, 2025