PERMIT #7106801-CN

9215 WOODLAWN AVE N, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 26, 2026
In Review
2 cycles
Reviews Done
March 9, 2026
Ready to Issue
March 10, 2026
Issued
March 10, 2026
Completed
Expires
September 10, 2027
42
Plan Review Days — Total
21
Plan Review Days — City Control
21
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$30,000
Type
Residential Construction
Issued
March 10, 2026
Location
Licton Springs

Contractor Information

Contractor
GROUNDWORKS
General Contractor
License GROUN**763O5

Location & Map

Project Description
Pettigrew Foundation Repair Construct repairs to foundation of existing three-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GROUN**763O5
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0041527
Review cycles
2
Plan review days
42
Days in corrections
21
Expires
September 10, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor