PERMIT #7106885-CN

4138 A 44TH AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 12, 2025
In Review
3 cycles
Reviews Done
April 23, 2026
Ready to Issue
April 23, 2026
Issued
June 8, 2026
Completed
Expires
132
Plan Review Days — Total
111
Plan Review Days — City Control
21
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$671,017
Type
Residential Construction
Issued
June 8, 2026
Location
West Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct west two-family dwelling per plan. (Establish use as townhouse per land use code. Construct (2) two-family dwelling per plan. Review and processing for two records under 7106885-CN)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1170769
Review cycles
3
Plan review days
132
Days in corrections
21
Units added
2
Units removed
1
Open Map