PERMIT #7106938-CN
4601 6TH AVE S, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 23, 2025
In Review
3 cycles
Reviews Done
January 6, 2026
Ready to Issue
January 8, 2026
Issued
January 8, 2026
Completed
—
Expires
July 8, 2027
105
Plan Review Days — Total
68
Plan Review Days — City Control
37
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$350,000
Type
Industrial Construction
Issued
January 8, 2026
Location
Georgetown
Contractor Information
Location & Map
Project Description
Seattle 5 - Slab Repair Tenant improvements for warehouse (Seattle 5) at ground floor of existing industrial building, occupy per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CONCRCN024K6
Review level
Full +
Primary use
Industrial
Parcel
DV0037551
Review cycles
3
Plan review days
105
Days in corrections
37
Expires
July 8, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0