PERMIT #7107062-CN
2901 27TH AVE S, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 22, 2025
In Review
4 cycles
Reviews Done
June 10, 2026
Ready to Issue
June 10, 2026
Issued
June 11, 2026
Completed
—
Expires
—
261
Plan Review Days — Total
50
Plan Review Days — City Control
211
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$620,000
Type
Commercial Construction
Issued
June 11, 2026
Location
Beacon Hill
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct alterations to remove western portion of building in existing industrial building per plan.
Additional Details
Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0022053
Review cycles
4
Plan review days
261
Days in corrections
211
Units added
0
Units removed
0