PERMIT #7107132-DM
4147 44TH AVE SW, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
January 30, 2026
In Review
1 cycle
Reviews Done
February 11, 2026
Ready to Issue
February 12, 2026
Issued
March 19, 2026
Completed
July 29, 2026
Expires
September 19, 2027
12
Plan Review Days — Total
12
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
4147 44TH AVE SW, SEATTLE, WA Property
Demolition at 4147 44TH AVE SW Project
West Seattle Neighborhood
Project Overview
Project Details
Value
$800,000
Type
Residential Construction
Issued
March 19, 2026
Location
West Seattle
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Demolition Permit Demolish existing one-family dwelling and detached accessory garage, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0030097
Review cycles
1
Plan review days
12
Days in corrections
0
Expires
September 19, 2027