PERMIT #7107198-CN
4316 DAYTON AVE N, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 25, 2025
In Review
3 cycles
Reviews Done
March 25, 2026
Ready to Issue
March 26, 2026
Issued
March 26, 2026
Completed
—
Expires
September 26, 2027
90
Plan Review Days — Total
52
Plan Review Days — City Control
38
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$78,055
Type
Residential Construction
Issued
March 26, 2026
Location
Fremont
Contractor Information
Location & Map
Project Description
Taverniti ADU Addition Establish use as single-family residence and a detached accessory dwelling unit per land use code. Allow new detached accessory dwelling unit to existing single family use. Construct new one family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
LCMBUCM872PT
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1153995
Review cycles
3
Plan review days
90
Days in corrections
38
Expires
September 26, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0