PERMIT #7107283-CN
834 B NE 102ND ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 8, 2025
In Review
3 cycles
Reviews Done
December 31, 2025
Ready to Issue
January 5, 2026
Issued
January 19, 2026
Completed
—
Expires
July 19, 2027
84
Plan Review Days — Total
53
Plan Review Days — City Control
31
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$408,419
Type
Residential Construction
Issued
January 19, 2026
Location
Maple Leaf
Contractor Information
Location & Map
Project Description
Maple Leaf Unit 2 Establish use as single-family dwelling unit, per land use code. Construct new one-family dwelling, per plan. (Units 1/4 & 3 under separate permit)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
TRINIBL761R3
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1159488
Review cycles
3
Plan review days
84
Days in corrections
31
Expires
July 19, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0