PERMIT #7107328-CN
812 N 42ND ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 31, 2025
In Review
2 cycles
Reviews Done
December 5, 2025
Ready to Issue
December 9, 2025
Issued
December 15, 2025
Completed
—
Expires
June 15, 2027
35
Plan Review Days — Total
14
Plan Review Days — City Control
21
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
812 N 42ND ST, SEATTLE, WA Property
Renovation at 812 N 42ND ST Project
CHAIN CONSTRUCTION LLC Contractor
Fremont Neighborhood
Project Overview
Project Details
Value
$50,000
Type
Residential Construction
Issued
December 15, 2025
Location
Fremont
Contractor Information
Location & Map
Project Description
Egress Stairs Replacement Construct alterations to multifamily building (replace collapsed exterior egress stairway), per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CHAINCL825NU
Review level
Full +
Primary use
Multifamily
Parcel
DV0052800
Review cycles
2
Plan review days
35
Days in corrections
21
Expires
June 15, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0