PERMIT #7107481-CN
1445 S HENDERSON ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 4, 2025
In Review
2 cycles
Reviews Done
February 3, 2026
Ready to Issue
February 5, 2026
Issued
February 18, 2026
Completed
—
Expires
August 18, 2027
61
Plan Review Days — Total
45
Plan Review Days — City Control
16
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$30,437
Type
Industrial Construction
Issued
February 18, 2026
Location
Other Seattle
Contractor Information
Location & Map
Project Description
Boeing 15-008 Install Additional Plotter Table Construct addition and alterations to existing commercial building (Boeing Building 15-08), per plan. Mechanical included.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
OMEGAGI895J2
Review level
Full +
Primary use
Industrial
Parcel
DV0062400
Review cycles
2
Plan review days
61
Days in corrections
16
Expires
August 18, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0