PERMIT #7107913-CN

210 THOMAS ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 10, 2025
In Review
1 cycle
Reviews Done
October 22, 2025
Ready to Issue
October 23, 2025
Issued
October 27, 2025
Completed
November 19, 2025
Expires
April 27, 2027
12
Plan Review Days — Total
275
Days in Applicant Control
1
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Belltown Neighborhood

Project Overview

Project Details
Value
$1,000,000
Type
Commercial Construction
Issued
October 27, 2025
Location
Belltown

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
2025 Seattle Christmas Market Erect (6) temporary structures for Christmas Market from 11/20 - 12/24/2025, per plan. [All components provided and assembled by professional crew. Owner responsible for structural integrity of all structures]

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Commercial
Parcel
DV0361800
Review cycles
1
Plan review days
12
Days in corrections
275
Expires
April 27, 2027
Open official SDCI detail →
Open Map