PERMIT #7108199-CN
370 THOMAS ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
March 11, 2026
In Review
3 cycles
Reviews Done
June 25, 2026
Ready to Issue
June 26, 2026
Issued
June 29, 2026
Completed
—
Expires
—
106
Plan Review Days — Total
76
Plan Review Days — City Control
30
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$15,000,000
Type
Commercial Construction
Issued
June 29, 2026
Location
Belltown
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct alterations to renovate historic Seattle Center Monorail Station per plan. Mechanical work included this permit.
Additional Details
Permit Intelligence
Review level
Full C
Primary use
Institutional
Parcel
DV0357738
Review cycles
3
Plan review days
106
Days in corrections
30
Units added
0
Units removed
0