PERMIT #7108451-CN

1620 BELMONT AVE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 22, 2025
In Review
2 cycles
Reviews Done
May 6, 2026
Ready to Issue
May 7, 2026
Issued
June 15, 2026
Completed
Expires
196
Plan Review Days — Total
87
Plan Review Days — City Control
109
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Capitol Hill Neighborhood

Project Overview

Project Details
Value
$1,346,615
Type
Residential Construction
Issued
June 15, 2026
Location
Capitol Hill

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct alterations to exterior envelope of multi-family building [THE PRESS CONDOMINIUMS NORTH BUILDING 2] per plan.

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Multifamily
Parcel
DV0056901
Review cycles
2
Plan review days
196
Days in corrections
109
Units added
0
Units removed
0
Open Map