PERMIT #7108466-CN
4563 34TH AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 21, 2026
In Review
4 cycles
Reviews Done
May 26, 2026
Ready to Issue
May 27, 2026
Issued
May 27, 2026
Completed
—
Expires
November 27, 2027
125
Plan Review Days — Total
71
Plan Review Days — City Control
54
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$673,052
Type
Residential Construction
Issued
May 27, 2026
Location
Magnolia
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit Establish use as single family residence with attached accessory dwelling unit per land use code. Construct new two-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1125568
Review cycles
4
Plan review days
125
Days in corrections
54
Expires
November 27, 2027
Existing units
0
Units added
2
Units removed
1
Sleeping rooms
0