PERMIT #7108470-CN

8320 B 30TH AVE NW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 9, 2025
In Review
4 cycles
Reviews Done
June 18, 2026
Ready to Issue
June 22, 2026
Issued
June 26, 2026
Completed
Expires
252
Plan Review Days — Total
131
Plan Review Days — City Control
121
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ballard Neighborhood

Project Overview

Project Details
Value
$679,887
Type
Residential Construction
Issued
June 26, 2026
Location
Ballard

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct new west one family dwelling per plan (Establish use as single family residence with detached accessory dwelling unit per land use code. Construct 2 new one-family dwellings per plan. Review and processing for two records under 7108470-CN)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1198967
Review cycles
4
Plan review days
252
Days in corrections
121
Units added
1
Units removed
0
Open Map