PERMIT #7108471-DM
8320 30TH AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 25, 2025
In Review
5 cycles
Reviews Done
June 3, 2026
Ready to Issue
June 7, 2026
Issued
June 7, 2026
Completed
—
Expires
—
190
Plan Review Days — Total
73
Plan Review Days — City Control
117
Days in Applicant Control
5
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$400,000
Type
Residential Construction
Issued
June 7, 2026
Location
Ballard
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Demolish existing one family dwelling and site structures per plan.
Additional Details
Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1198967
Review cycles
5
Plan review days
190
Days in corrections
117