PERMIT #7108557-CN
1301 5TH AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 23, 2025
In Review
1 cycle
Reviews Done
January 14, 2026
Ready to Issue
May 6, 2026
Issued
May 19, 2026
Completed
—
Expires
November 19, 2027
22
Plan Review Days — Total
22
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$200,640
Type
Commercial Construction
Issued
May 19, 2026
Location
Downtown
Contractor Information
Location & Map
Project Description
MILLIMAN Construct tenant improvements to the north central portion at Levels 37 & 39 of exiting office building (Rainier Tower), and occupy per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SKYLIC*773DW
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0029706
Review cycles
1
Plan review days
22
Days in corrections
0
Expires
November 19, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0