PERMIT #7108732-CN

10124 66TH AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 7, 2026
In Review
2 cycles
Reviews Done
May 22, 2026
Ready to Issue
May 26, 2026
Issued
May 26, 2026
Completed
Expires
November 26, 2027
135
Plan Review Days — Total
30
Plan Review Days — City Control
105
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ben Davidson Contractor
Rainier Beach Neighborhood

Project Overview

Project Details
Value
$244,040
Type
Residential Construction
Issued
May 26, 2026
Location
Rainier Beach

Contractor Information

Contractor
Ben Davidson
Single Family/Duplex
License PREMICR939QR

Location & Map

Project Description
Ralkowski Hutchinson 2F Construct substantial alterations to existing one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PREMICR939QR
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0074486
Review cycles
2
Plan review days
135
Days in corrections
105
Expires
November 26, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor