PERMIT #7108796-CN
5706 35TH AVE NE, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
October 7, 2025
In Review
2 cycles
Reviews Done
December 3, 2025
Ready to Issue
December 8, 2025
Issued
December 9, 2025
Completed
April 17, 2026
Expires
June 9, 2027
57
Plan Review Days — Total
43
Plan Review Days — City Control
14
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
5706 35TH AVE NE, SEATTLE, WA Property
Renovation at 5706 35TH AVE NE Project
GROUNDWORKS Contractor
Ravenna Neighborhood
Project Overview
Project Details
Value
$45,000
Type
Residential Construction
Issued
December 9, 2025
Location
Ravenna
Contractor Information
Location & Map
Project Description
Bain Foundation Repair Construct alterations for foundation repair of existing 1-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GROUN**763O5
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1173542
Review cycles
2
Plan review days
57
Days in corrections
14
Expires
June 9, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0