PERMIT #7108959-CN

5412 KENSINGTON PL N, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
February 11, 2026
In Review
2 cycles
Reviews Done
March 24, 2026
Ready to Issue
March 26, 2026
Issued
March 26, 2026
Completed
Expires
September 26, 2027
41
Plan Review Days — Total
35
Plan Review Days — City Control
6
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$190,621
Type
Residential Construction
Issued
March 26, 2026
Location
Green Lake

Contractor Information

Contractor
WALT KANE CONSTRUCTION LLC
General Contractor
License WALTKKC793M7

Location & Map

Project Description
5412 Kensington Pl N - Construction - Kensington Pl N Remodel Construct substantial alterations and additions for one-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
WALTKKC793M7
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1204807
Review cycles
2
Plan review days
41
Days in corrections
6
Expires
September 26, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
2
Open official SDCI detail →
View Contractor