PERMIT #7109009-CN
521 STADIUM PL S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
September 27, 2025
In Review
0 cycles
Ready to Issue
September 29, 2025
Issued
October 7, 2025
Completed
May 27, 2026
Expires
April 7, 2027
0
Days in Applicant Control
0
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
521 STADIUM PL S, SEATTLE, WA Property
VENTURE GENERAL CONTRCTNG LLC Contractor
Other Seattle Neighborhood
Project Overview
Project Details
Value
$177,000
Type
Residential Construction
Issued
October 7, 2025
Location
Other Seattle
Contractor Information
Location & Map
Project Description
521 Stadium Pl S - Construction - NOLO Tower Rooftop 11th Floor STFI Construct interior non-structural tenant improvements to include demolition and reconfiguration of spaces with updated finishes and decorative elements on the 11th-floor level of mixed-use apartment building [STADIUM PLACE NOLO TOWER], subject to field inspection [STFI].
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VENTUGC899LZ
Review level
Field
Primary use
Multifamily
Parcel
DV0078423
Review cycles
0
Days in corrections
0
Expires