PERMIT #7109009-CN

521 STADIUM PL S, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 27, 2025
In Review
0 cycles
Ready to Issue
September 29, 2025
Issued
October 7, 2025
Completed
May 27, 2026
Expires
April 7, 2027
0
Days in Applicant Control
0
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$177,000
Type
Residential Construction
Issued
October 7, 2025
Location
Other Seattle

Contractor Information

Contractor
VENTURE GENERAL CONTRCTNG LLC
General Contractor
License VENTUGC899LZ

Location & Map

Project Description
521 Stadium Pl S - Construction - NOLO Tower Rooftop 11th Floor STFI Construct interior non-structural tenant improvements to include demolition and reconfiguration of spaces with updated finishes and decorative elements on the 11th-floor level of mixed-use apartment building [STADIUM PLACE NOLO TOWER], subject to field inspection [STFI].

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VENTUGC899LZ
Review level
Field
Primary use
Multifamily
Parcel
DV0078423
Review cycles
0
Days in corrections
0
Expires
April 7, 2027