PERMIT #7109550-CN
3633 35TH AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 3, 2025
In Review
3 cycles
Reviews Done
February 19, 2026
Ready to Issue
March 10, 2026
Issued
March 10, 2026
Completed
—
Expires
September 10, 2027
108
Plan Review Days — Total
37
Plan Review Days — City Control
71
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$150,000
Type
Residential Construction
Issued
March 10, 2026
Location
Magnolia
Contractor Information
Location & Map
Project Description
Balasubramanyam D'Souza Construct sport court for existing one-family residence, per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
AXIOMCL002MO
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0089842
Review cycles
3
Plan review days
108
Days in corrections
71
Expires
September 10, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0