PERMIT #7109647-CN

6519 NE 61ST ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 14, 2026
In Review
2 cycles
Reviews Done
June 5, 2026
Ready to Issue
June 5, 2026
Issued
June 23, 2026
Completed
Expires
142
Plan Review Days — Total
68
Plan Review Days — City Control
74
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Other Seattle Neighborhood

Project Overview

Project Details
Value
$837,880
Type
Residential Construction
Issued
June 23, 2026
Location
Other Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Establish use as single family dwelling unit with an attached accessory dwelling unit per land use code. Construct as two-family dwelling with attached garage per plan.

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0078936
Review cycles
2
Plan review days
142
Days in corrections
74
Units added
2