PERMIT #7109700-CN
4115 ROOSEVELT WAY NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 3, 2025
In Review
7 cycles
Reviews Done
June 17, 2026
Ready to Issue
June 18, 2026
Issued
June 18, 2026
Completed
—
Expires
—
257
Plan Review Days — Total
63
Plan Review Days — City Control
194
Days in Applicant Control
7
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
4115 ROOSEVELT WAY NE, SEATTLE, WA Property
Wallingford Neighborhood
Project Overview
Project Details
Value
$30,000
Type
Residential Construction
Issued
June 18, 2026
Location
Wallingford
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct alterations to minor telecommunications facility (AT&T) at the roof level of mixed-use building per plan.
Additional Details
Permit Intelligence
Review level
Full +
Primary use
Multifamily
Parcel
DV0038671
Review cycles
7
Plan review days
257
Days in corrections
194
Units added
0
Units removed
0