PERMIT #7109960-CN

10551 A 41ST PL NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 3, 2025
In Review
0 cycles
Reviews Done
April 14, 2026
Ready to Issue
April 16, 2026
Issued
April 16, 2026
Completed
Expires
October 16, 2027
193
Plan Review Days — Total
193
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$350,157
Type
Residential Construction
Issued
April 16, 2026
Location
Meadowbrook

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
HERNANDEZ CAPITAL LLC 41ST PLACE Construct new middle one family dwelling, per plan. (Establish use as single family residence with attached and detached accessory dwelling units per land use code. Construct 1 two family dwelling and 2 one family dwellings, per plan. Review and processing for 3 records under 7065466-CN)

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV1126440
Review cycles
0
Plan review days
193
Days in corrections
0
Expires
October 16, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →