PERMIT #7109997-CN

7323 31ST AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 1, 2025
In Review
3 cycles
Reviews Done
February 26, 2026
Ready to Issue
March 12, 2026
Issued
March 12, 2026
Completed
Expires
September 12, 2027
87
Plan Review Days — Total
41
Plan Review Days — City Control
46
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
West Seattle Neighborhood

Project Overview

Project Details
Value
$204,174
Type
Residential Construction
Issued
March 12, 2026
Location
West Seattle

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
NEW DADU Allow new detached accessory dwelling unit to existing single family use per land use code. Construct new one family dwelling, per plan. Project includes removal of detached accessary building (Shed).

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1126465
Review cycles
3
Plan review days
87
Days in corrections
46
Expires
September 12, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
3
Open official SDCI detail →