PERMIT #7110111-CN
9306 31ST AVE SW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 26, 2026
In Review
3 cycles
Reviews Done
April 29, 2026
Ready to Issue
May 27, 2026
Issued
May 27, 2026
Completed
—
Expires
—
93
Plan Review Days — Total
53
Plan Review Days — City Control
40
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
9306 31ST AVE SW, SEATTLE, WA Property
Renovation at 9306 31ST AVE SW Project
White Center Neighborhood
Project Overview
Project Details
Value
$150,097
Type
Residential Construction
Issued
May 27, 2026
Location
White Center
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct substantial alterations and additions to an existing one family dwelling per plan.
Additional Details
Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0024450
Review cycles
3
Plan review days
93
Days in corrections
40
Units added
0
Units removed
0