PERMIT #7110111-CN

9306 31ST AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 26, 2026
In Review
3 cycles
Reviews Done
April 29, 2026
Ready to Issue
May 27, 2026
Issued
May 27, 2026
Completed
Expires
93
Plan Review Days — Total
53
Plan Review Days — City Control
40
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
White Center Neighborhood

Project Overview

Project Details
Value
$150,097
Type
Residential Construction
Issued
May 27, 2026
Location
White Center

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct substantial alterations and additions to an existing one family dwelling per plan.

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0024450
Review cycles
3
Plan review days
93
Days in corrections
40