PERMIT #7110321-CN

116 N 55TH ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 13, 2026
In Review
2 cycles
Reviews Done
February 12, 2026
Ready to Issue
February 12, 2026
Issued
February 12, 2026
Completed
Expires
August 12, 2027
30
Plan Review Days — Total
25
Plan Review Days — City Control
5
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$329,592
Type
Residential Construction
Issued
February 12, 2026
Location
Phinney Ridge

Contractor Information

Contractor
REAL PROPERTY FUNDING GRP LLC
General Contractor
License REALPPF855N5

Location & Map

Project Description
Construction Permit Establish use as single-family residence, per land use code. Construct new one-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
REALPPF855N5
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1172029
Review cycles
2
Plan review days
30
Days in corrections
5
Expires
August 12, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor