PERMIT #7110559-CN

8536 LATONA AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 12, 2025
In Review
4 cycles
Reviews Done
April 17, 2026
Ready to Issue
April 17, 2026
Issued
April 17, 2026
Completed
Expires
October 17, 2027
126
Plan Review Days — Total
58
Plan Review Days — City Control
68
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
NWGC Contractor
Green Lake Neighborhood

Project Overview

Project Details
Value
$207,207
Type
Residential Construction
Issued
April 17, 2026
Location
Green Lake

Contractor Information

Contractor
NWGC
General Contractor
License NWGC***754MP

Location & Map

Project Description
8538 Latona Ave NE - Construction - Petersen Maple Leaf Cabin Allow one detached accessory dwelling unit, per land use code. Construct one-family dwelling, per plan. Existing one-family dwelling to remain.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
NWGC***754MP
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1185506
Review cycles
4
Plan review days
126
Days in corrections
68
Expires
October 17, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor