PERMIT #7110562-CN

2344 HALLECK AVE SW, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 21, 2025
In Review
3 cycles
Reviews Done
January 29, 2026
Ready to Issue
January 29, 2026
Issued
January 30, 2026
Completed
April 24, 2026
Expires
July 30, 2027
100
Plan Review Days — Total
56
Plan Review Days — City Control
44
Days in Applicant Control
3
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$70,000
Type
Residential Construction
Issued
January 30, 2026
Location
West Seattle

Contractor Information

Contractor
GROUNDWORKS
General Contractor
License GROUN**763O5

Location & Map

Project Description
Geroux Foundation Repair Install push and helical piles to stabilize portions of existing one-family residence, per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GROUN**763O5
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1142195
Review cycles
3
Plan review days
100
Days in corrections
44
Expires
July 30, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →