PERMIT #7110761-CN
8320 30TH AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 9, 2025
In Review
0 cycles
Reviews Done
June 18, 2026
Ready to Issue
June 22, 2026
Issued
June 26, 2026
Completed
—
Expires
—
252
Plan Review Days — Total
252
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$99,704
Type
Residential Construction
Issued
June 26, 2026
Location
Ballard
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct new one family dwelling per plan. (Establish use as single family residence with detached accessory dwelling unit per land use code. Construct 2 new one family dwellings per plan. Review and processing for two records under 7108470-CN)
Additional Details
Permit Intelligence
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV1198967
Review cycles
0
Plan review days
252
Days in corrections
0
Units added
1
Units removed
0