PERMIT #7111041-CN

4113 SW IDA ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 12, 2025
In Review
4 cycles
Reviews Done
April 6, 2026
Ready to Issue
April 6, 2026
Issued
May 22, 2026
Completed
Expires
November 22, 2027
115
Plan Review Days — Total
76
Plan Review Days — City Control
39
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
West Seattle Neighborhood

Project Overview

Project Details
Value
$479,242
Type
Residential Construction
Issued
May 22, 2026
Location
West Seattle

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Construction Permit Construct new north two-family dwelling, per plan. (Establish use as single-family dwelling unit with an attached accessory dwelling unit and establish use as townhouses, per land use code.) Construct new one- and two-family dwellings, per plan. Review and processing for two records under 7111041-CN.)

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0053178
Related land-use permit
3043452-LU
Review cycles
4
Plan review days
115
Days in corrections
39
Expires
November 22, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map