PERMIT #7111136-BK

1700 WESTLAKE AVE N, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 10, 2025
In Review
2 cycles
Reviews Done
October 30, 2025
Ready to Issue
October 31, 2025
Issued
November 3, 2025
Completed
January 21, 2026
Expires
May 3, 2027
20
Plan Review Days — Total
18
Plan Review Days — City Control
2
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$100,000
Type
Commercial Construction
Issued
November 3, 2025
Location
South Lake Union

Contractor Information

Contractor
J E CUMMING CORP
General Contractor
License JECUMC*148JH

Location & Map

Project Description
Terrell Marshall Construct blanket permit tenant improvements to Terrell Marshall Law Group PLLC on the third floor of existing commercial building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
JECUMC*148JH
Review level
Full C
Primary use
Commercial
Parcel
DV0013941
Review cycles
2
Plan review days
20
Days in corrections
2
Expires
May 3, 2027
Open official SDCI detail →
View Contractor