PERMIT #7111628-CN

2755 NW 90TH ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
November 4, 2025
In Review
4 cycles
Reviews Done
March 31, 2026
Ready to Issue
March 31, 2026
Issued
March 31, 2026
Completed
April 1, 2026
Expires
September 30, 2027
147
Plan Review Days — Total
92
Plan Review Days — City Control
55
Days in Applicant Control
4
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Other Seattle Neighborhood

Project Overview

Project Details
Value
$209,093
Type
Residential Construction
Issued
March 31, 2026
Location
Other Seattle

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
DADU #2 - Construction Permit Allow second new detached accessory dwelling unit (DADU) to existing single family use per land use code. Construct new northwest one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1220825
Review cycles
4
Plan review days
147
Days in corrections
55
Expires
September 30, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map