PERMIT #7111670-CN
9257 VIEW AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 27, 2026
In Review
2 cycles
Reviews Done
March 26, 2026
Ready to Issue
April 1, 2026
Issued
April 7, 2026
Completed
—
Expires
October 7, 2027
58
Plan Review Days — Total
30
Plan Review Days — City Control
28
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
9257 VIEW AVE NW, SEATTLE, WA Property
Renovation at 9257 VIEW AVE NW Project
TRIPLE BOTTOM LINE CNSTRTN SPC Contractor
Other Seattle Neighborhood
Project Overview
Project Details
Value
$150,000
Type
Residential Construction
Issued
April 7, 2026
Location
Other Seattle
Contractor Information
Location & Map
Project Description
Entry Repairs Construct alterations to existing one family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
TRIPLBL824M6
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0091123
Review cycles
2
Plan review days
58
Days in corrections
28
Expires
October 7, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0