PERMIT #7111695-CN

3033 28TH AVE W, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 29, 2025
In Review
2 cycles
Reviews Done
November 19, 2025
Ready to Issue
November 19, 2025
Issued
November 20, 2025
Completed
June 3, 2026
Expires
May 20, 2027
21
Plan Review Days — Total
15
Plan Review Days — City Control
6
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
GROUNDWORKS Contractor
Magnolia Neighborhood

Project Overview

Project Details
Value
$14,500
Type
Residential Construction
Issued
November 20, 2025
Location
Magnolia

Contractor Information

Contractor
GROUNDWORKS
General Contractor
License GROUN**763O5

Location & Map

Project Description
Stanton - Foundation Repair - (3) pin piles Foundation repairs to one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GROUN**763O5
Housing category
Single-Family Add/Alt
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV1100509
Review cycles
2
Plan review days
21
Days in corrections
6
Expires
May 20, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor