PERMIT #7111734-CN
5729 35TH AVE NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 15, 2025
In Review
0 cycles
Reviews Done
April 14, 2026
Ready to Issue
April 14, 2026
Issued
April 14, 2026
Completed
—
Expires
October 14, 2027
181
Plan Review Days — Total
181
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$264,094
Type
Residential Construction
Issued
April 14, 2026
Location
Ravenna
Contractor Information
Location & Map
Project Description
5729 35th Ave NE - Construction - Unit 2 (MIDDLE unit) Construct middle one-family dwelling, per plan. (Establish use as housing for (3) detached dwelling units, per land use code. Construct one-family dwellings, per plan. Review and processing for (3) construction records under 7091762-CN.)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
LOCALBH761Q2
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV0358759
Review cycles
0
Plan review days
181
Days in corrections
0
Expires
October 14, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0