PERMIT #7111749-CN

1705 NE PACIFIC ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 21, 2025
In Review
3 cycles
Reviews Done
January 29, 2026
Ready to Issue
April 21, 2026
Issued
April 21, 2026
Completed
Expires
October 21, 2027
100
Plan Review Days — Total
24
Plan Review Days — City Control
76
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$675,000
Type
Commercial Construction
Issued
April 21, 2026
Location
University District

Contractor Information

Contractor
JTM CONSTRUCTION INC
General Contractor
License JTMCOCI813DL

Location & Map

Project Description
Construction Permit: lvl 2 TI Interior tenant improvement at level 2 of existing institutional building, occupy per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
JTMCOCI813DL
Review level
Full +
Primary use
Institutional
Parcel
DV0010348
Review cycles
3
Plan review days
100
Days in corrections
76
Expires
October 21, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →