PERMIT #7111795-BK

5601 6TH AVE S, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 15, 2025
In Review
3 cycles
Reviews Done
January 7, 2026
Ready to Issue
January 8, 2026
Issued
January 16, 2026
Completed
March 30, 2026
Expires
July 16, 2027
84
Plan Review Days — Total
64
Plan Review Days — City Control
20
Days in Applicant Control
3
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$90,000
Type
Commercial Construction
Issued
January 16, 2026
Location
Georgetown

Contractor Information

Contractor
METROPOLITAN CONTRACTING LLC
General Contractor
License METROCL974ON

Location & Map

Project Description
Helly Hansen Office: Suite #274 TI Construct blanket permit tenant improvements to Helly Hansen on the second floor (suite #274) of existing commercial building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
METROCL974ON
Review level
Full C
Primary use
Commercial
Parcel
DV0026160
Review cycles
3
Plan review days
84
Days in corrections
20
Expires
July 16, 2027
Open official SDCI detail →